2023 IW Consolidated Dewater Project Update
"Douglas Morgan provides an update on the progress of the dewater project at Marseilles Lock, Dresden Island, and Brandon Road Lock. See images of key milestones achieved, including gate installations, concrete placements, and machinery anchors. Stay informed about the ongoing developments in lock and dam infrastructure improvements."
Uploaded on Mar 03, 2025 | 0 Views
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
2023 IW CONSOLIDATED DEWATER PROJECT UPDATE Douglas Morgan Chief of Locks and Dams MVD-MVR-ODI 16 August 2023
MARSEILLES LOCK Lower miter gate quoin blocks being fitted. Wall armor installed ahead of concrete placement next week. Back fill work on land wall side begins.
DRESDEN ISLAND Bull gear machinery anchors installed ahead of concrete pour . Precast valve section installation on lower end progressing. Upper valve hole concrete removal in progress. Upper sill extension is now complete.
BRANDON ROAD LOCK Upper right gate machinery installed. New beams going in for valve intake screens. Concrete placement for top of new sill.