Booster and AGS Operations Update - May 5, 2025
Stay updated on the latest operations at Accelerator, including maintenance schedules, repair updates, and moisture mitigation efforts. Join the 3 pm meeting for important discussions and streaming updates.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Time meeting Accelerator Operations Support Paul Sampson 05/05/2025
Long day in Booster and AGS for new fire detection commissioning LINAC RF area Access today, Injector Maintenance tomorrow Both in RA most of the day LINAC Zones 3&4 access tomorrow here Meeting here at 3pm and streaming
MAIN LINE CLOSED, LEAK TIGHT RHIC repair update : RUSH LINES AT D0-Q1 WELDED TODAY, PUMPING DOWN NOW FINAL WELDS AWAITING RESOLUTION OF HI-POT ISSUES POD MEETINGS DAILY Streaming STREAMING AND HERE HERE PROGRESS UPDATED IN REAL TIME HERE
Mitigating Moisture ESF, F&O, CAD all working to reduce moisture in valve boxes Heat, AC, and air recirculation being added PSG working with others, diagnosis continues
Access cartoon from This_Week (https://www.agsrhichom e.bnl.gov/AGS/Accel/Main tenance/Schedules/This_ week.htm#daily )