Compton High School Construction Project Details
Explore the comprehensive details of the Compton High School construction project, including budget allocations, revenue received, and expenditures. Learn about the facilities being built on the campus, such as academic buildings, performance arts centers, gymnasiums, and more. Dive deep into the financial aspects and progress updates of the project.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
MEASURE S & AAA JANUARY CABINET PRESENTATION
MEASURE S November 3, 2015 = voters approved $350,000,000 (55.4% passage rate) Issued for the purpose of making schools modern, safe and inspiring; to reconstruct local schools and facilities, including libraries, modern classrooms and science labs, media and performing arts centers, technology centers and athletic complexes; to improve safety, security, roofing, plumbing heating, electrical, and other systems
Measure S Revenue Received/Available as of January 2024 = $262,924,474 Date Revenue Issuance Received October 2016 Series A $20,000,000 $19,737,851 August 2019 Series B $229,996,080 $229,645,330 September 2017 Dre Donation $9,929,686 Ongoing Interest $3,611,607 Unissued 2025 Series C $100,003,920 TBD $350,000,000 TBD
Measure S Expenditures Expenditures as of January 2024 = $113,627,220 CHS Budget Commitments = $320,049,726 Site Demo & Environmental $ 11,344,515 Design $ 12,877,371 Construction (Site, add on field & fieldhouse) $237,307,971 Construction Support Costs (Cummings, DSA, F&E) $ 23,157,255 Contingency $ 9,028,876 Budget Commitments $320,049,726
Compton High School = $201,530,000 - Jan 2025 Construction of a replacement high school facility on 30 acres with a two-story Academic Building (140,639 SF) with forty-two (42) classrooms, eight (8) science labs, four (4) physics labs, five (5) Career Technical Education (CTE) workshops, student dining, lunch shelter, kitchen and administration offices; a one-story Performance Arts Center (40,868 SF) with a 900 seat auditorium, lobby, concessions & ticketing, dance & drama studio, orchestra room, chorus room, digital music lab and video production lab; a one- story Gymnasium (36,534 SF) with one (1) main basketball court or three (3) practice basketball courts, Boys & Girls locker rooms, lobby, concessions & ticketing, weight room, training room, fitness room, wrestling room and swimming pool stadium. Site improvements include a new Football Stadium with track and field, aluminum bleachers, a 390 SF press box, a visitor s restroom and concession building, eight (8) tennis courts, four (4) outdoor basketball courts, parking lots and a California Native Landscaped outdoor environment.
Compton High School; Athletic Fields = $33m Modernize existing Baseball, Softball and Soccer Fields to include a new One-Story 10,000SF Fieldhouse, a new Baseball Field, a new Softball Field, a new Soccer Field and new Walking Paths and Gardens.
MEASURE AAA November 8, 2022 = voters approved $350,000,000 (77.6% passage rate) Issued for the purpose of fixing deteriorating roofs, plumbing, heating, electrical, and other systems, enhance school safety, and construct, reconstruct, renovate, rehabilitate and modernize classrooms, sites and facilities, including media and performing arts centers, technology centers and athletic complexes Centennial HS - new full Site Construction project; architect selection February 2024 Dominguez HS - new Cafeteria/Kitchen project