Energy Program Updates & Low-Income Needs Assessment Timeline
Stay informed with the latest updates on the ESA and CARE programs, including disconnection updates and the post-2020 guidance. Explore the timeline for the Low-Income Needs Assessment for 2019, detailing research activities and data collection strategies.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
ESA and CARE Program Proceeding Updates Staff Briefing for the Low Income Oversight Board (LIOB) Meeting December 5th, 2018 Energy Division California Public Utilities Commission (CPUC) 1
Disconnection OIR Update CARE/ESA Post 2020 Guidance Low Income Needs Assessment 2
Disconnection OIR Update Phase 1 will examine current policies and changes that can be made to reduce disconnections to a target by January 1 2024. Proposed decision in Phase 1 by 2nd quarter 2019. Phase II will take a broader look at the disconnection process and ways to completely prevent it. Upcoming Workshops 12/6 in Stockton Energy Division will provide a workshop report in late January 2019. 3
CARE/ESA Post 2020 Guidance The Commission s Guidance Decision is targeted for 1st quarter 2019 in preparation for the IOU budget application filings which are due June 1, 2019. A Commission Decision addressing the Budget Applications and post 2020 low income programs is anticipated 4th quarter 2020. 5
2019 Low Income Needs Assessment (LINA) Timeline 2018 6/1 2019 1/1 Task Research Plan Activity Study team and stakeholders review Finalize plan Submit data requests and obtain data Develop sampling plan Develop ESA contractor interview/focus group guides Develop CBO interview guide Develop customer survey instruments Conduct CBO interviews Conduct ESA contractor interviews/focus groups Develop analysis plan Pre-test and field customer surveys Conduct preliminary analyses Preliminary Results Review Review draft analyses Prepare draft final report Distribute draft report Prepare presentation deck Hold workshop Respond to comments and revise report Post final report and deliver data sets 7/1 8/1 9/1 10/1 11/1 12/1 2/1 3/1 4/1 5/1 6/1 7/1 8/1 9/1 10/1 11/1 12/1 Data Collection Analysis Report 7
2022 Low Income Needs Assessment Projected Activity & Timeline Public workshops and opportunities for stakeholder engagement throughout process, will sync and align with LIOB Board meetings or subcommittee meetings where feasible. The initial planning phase for the 2022 LINA will begin once the 2019 assessment is finalized. Energy Division will coordinate with the Board and IOUs to initiate this effort and see it through to completion. Preliminary Project Timeline: PY 2020 /Topic Solicitation, RFP, Consultant Selection PY2021 / Draft & Final Research Plan / Data Collection PY 2022 / Data Collection /Draft & Final Reports 8