Energy Storage Resources: Base Point Deviation Charges Overview

ktc 7 base point deviation charges for energy n.w
1 / 6
Embed
Share

Explore the proposal for a new Base Point Deviation (BPD) settlement system for Energy Storage Resources (ESRs) incorporating tiered deviation tolerances. Learn about the single model ESR registration, SCED base point handling, telemetering, and settlement intervals. Discover the tiered deviation tolerances based on Average Aggregated Base Point (AABP) values for ESRs.

  • Energy Storage Resources
  • BPD Settlement
  • Deviation Tolerances
  • ESR Registration
  • Tiered Approach

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. KTC-7: Base Point Deviation Charges for Energy Storage Resources- Single Model Magie Shanks ERCOT BESTF Meeting 11/04/2019

  2. Overview Create a new Base Point Deviation (BPD) Settlement for the Single Model Energy Storage Resource (ESR). Incorporate proposal for tiered deviation tolerances for ESRs. 2 PUBLIC

  3. Base Point Deviation Settlement The ESR: Will be registered as a single Resource. Can receive both positive and negative SCED base points. Will telemeter generation/consumption as a single value, either positive or negative, for the Resource. BPD for ESR will mimic both the current BPD settlement for Generation Resources and Generation and Controllable Load Resource (GCLR) Group (proposed in NPRR963). 3 PUBLIC

  4. Base Point Deviation Settlement 10 8 OVER 6 4 Tolerance 2 Tolerance MWh 0 1 2 3 -2 Tolerance -4 UNDER -6 -8 Settlement Intervals Gen/Cons AABP 4 PUBLIC

  5. Deviation Tolerances Tiered Approach based on AABP for ESR AABP = AVGBP + AVGREG Proposed ESR Tolerances: ABS(AABP) 10 MW 3 MW or 3% of AABP ABS(AABP) > 10MW 5 MW or 5% of AABP 5 PUBLIC

  6. Questions? 6 PUBLIC