ERCOT Load Resource Changes in Upcoming RIOO Release

demand side working group dswg n.w
1 / 6
Embed
Share

Learn about the upcoming changes for Load Resources in the RIOO Release, including the new requirement to select load types and critical load attestations. ERCOT will work with Resource Entities to implement these updates effectively.

  • ERCOT
  • Load Resources
  • RIOO Release
  • Critical Load
  • Attestations

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Demand Side Working Group (DSWG) Changes for Load Resources in the Upcoming RIOO Release April 17, 2025 Donald House

  2. Changes for Load Resources in the upcoming RIOO release There are 2 changes impacting Load Resources (LRs) in the next RIOO update release on April 24, 2025 1. A new requirement to select the type of Load associated with each LR 2. Ability to view and update the Critical Load Attestation for each LR in RIOO Resource Services (RIOO RS) 2 PUBLIC

  3. Type of Load associated with LRs To improve ERCOT s visibility into the type of Load associated with each LR, ERCOT will start requiring this information during the initial registration process in RIOO The Resource Entity (RE) must select the type of Load from a dropdown list There will be a freeform data entry to provide additional details for some of the selections, but the list should cover most potential Load types This was discussed with DSWG on 1/27/2025, and a draft list was posted for review and comments on the 1/27/2025 DSWG meeting webpage The finalized list has also been posted to that same meeting page Future changes to the list can quickly be added to RIOO, as needed This field will be available for REs in RIOO RS to view and update ERCOT will work with REs to submit RIOO Change Requests (RSCRs) to add the type of Load for all existing LRs 3 PUBLIC

  4. Critical Load Attestations added to RIOO RS REs are required to complete the Critical Load Attestation for each new LR registered in RIOO IS Now, the RE will be able to view the current selection for each of their LRs in RIOO RS The RE will also be able to change their selection, if needed, by submitting an RSCR Note that condition 4 means that the Load is Critical; an LR can t be registered at a Critical Load 4 PUBLIC

  5. Critical Load Attestations added to RIOO RS ERCOT will pre-populate the field with the attestation condition currently on file for each LR ERCOT will ask REs to verify the data and to provide any missing selections or update the condition, as needed 5 PUBLIC

  6. Comments or questions? Comments or questions about LR registration data can be sent to the Demand Integration team at ERCOTLRandSODG@ercot.com 6 PUBLIC