EUREX Disaster Recovery Test Scenario Details

eurex n.w
1 / 6
Embed
Share

Explore the EUREX DR test scenario involving a partial outage of the primary data center facility, with available interfaces, test executions, and success criteria outlined. Understand the timeline for the test event on 05 October 2024.

  • EUREX
  • Disaster Recovery
  • Test Scenario
  • Data Center
  • DR Test

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. EUREX Scenario/Implications The DR test scenario simulates a partial outage of the primary data center facility (the co-location facility remains operational) The simulation back-end (located in another data center) is used as the DR production back-end T7 interfaces located in the primary data center will be switched to the simulation infrastructure and must be addressed using the simulation network addresses (see T7 Disaster Recovery Concept 2024 for details) 1

  2. EUREX (Contd) Available Interfaces The following T7 interfaces will be available during the DR test exercise: Enhanced Transaction Solution (ETI) FIX LF interface T7 GUI T7 Market Data Service (MDI) T7 Enhanced Market Data Service (EMDI) T7 Enhanced Order Book Interface (EOBI) Reference Data Interface (RDI) Common Report Engine (CRE) 2

  3. EUREX (Contd) Test Execution Customers participating in the DR test exercise can receive market data using the interfaces MDI, EMDI, EOBI and the T7 GUI read reference data using the RDI receive the Reference Data File (RDF) using the CRE enter orders and quotes using the interfaces ETI, FIX LF and the T7 GUI 3

  4. EUREX (Contd) Test Execution (cont d) Production reference data is used, including User IDs, T7 GUI keys, FIX LF and ETI sessions Please note: Changes made during the test exercise will not be copied back to production after the test. It is not recommended to make changes to this data during the test! 4

  5. EUREX (Contd) Success criteria for the DR test exercise The DR test exercise can be considered successful if one of the following three conditions is met either a message Connection Test ##### <hh:mm:ss> appears with an increasing sequence number in the market news view (news board) of the T7 Trader or Admin GUI or a successful session or trader login via ETI has been performed and MDI/EMDI/EOBI/RDI heartbeats have been received or a successful session or trader login via FIX LF has been performed and MDI/EMDI/EOBI/RDI heartbeats have been received 5

  6. EUREX (Contd) Timeline on 05 October 2024 Start of DR scenario test End of DR scenario test Start of prod environment re-connect test End of prod environment re-connect test 13:00 CEST 16:00 CEST 17:00 CEST 18:00 CEST Primary Contact Technical Key Account Manager (via individual VIP number) Detailed information Eurex Circular 080/2024 Updated version of T7 Disaster Recovery Concept 2024 - Accessible end of August under the following path: Eurex.com > Support > Initiatives & Releases > T7 Release 12.1 > Network Access 6