Financial Systems Modernization Executive Sponsor Briefing
"Stay updated on the Financial Systems Modernization project with insights from the Executive Sponsor briefing, including FAMIS project updates, Asysco enhancements, and readiness activities for application go-live. Get a comprehensive overview of project milestones, testing, security assessments, and performance improvements leading up to the launch. Stay informed and prepared for the upcoming changes in financial systems."
Uploaded on | 0 Views
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Financial Systems Modernization Executive Sponsor Briefing July 25, 2022 Mark Schulz Deputy CIO
Agenda Financial Systems Modernization FAMIS Project Update Asysco Update Annual Financial Report (AFR) Project Update Questions/Discussion 2
Overall Status Building detailed cut-over plan June 30 milestones complete Another round of User Acceptance Testing (UAT) completed in July 53 participants over the 3 days of testing for round 5 118 participants over all 5 rounds (January July) FAMIS response time (performance) work complete Security Assessment with Deloitte complete A few significant items identified Remediation plan under development
The Big Picture Readiness & Dress Rehearsals Application Ready Go Live June 30th 2022 November 2022 5
Application Ready Activities Percent Complete Task Name Status Finish Outstanding Defect and Gap Resolution 85% 9/30/22 Green Performance Testing and Updates 100% 6/30/22 Green Database Model Changes 100% 5/26/22 Green Job/Spool Management Tool 100% 5/26/22 Green Managed File Transfer (Go Anywhere) 99% 6/30/22 Green Green Control-M, WYLBUR, and JCL Changes 99% 6/30/22 6
Go-Live and Readiness - Activities Percent Complete Task Name Status Finish Infrastructure, D/R Site, and load balancing 100% 6/30/22 Green Security Assessment 100% 7/31/22 Green Control-M Conversion to Windows 50% 9/30/22 Green Custom dev for complex WYLBUR Processing 25% 9/30/22 Green Technical Staff Training 75% 8/31/22 Green User Acceptance Testing (UAT 5) 100% 7/31/22 Green 7
Asysco/Anubex Performance Enhancements Percent Complete Root Cause Status Description RC-1 Redefines 100% Green RC-2 RC-3 RC-4 RC-5 Optimized Index Updates Optimize *Number Laserfiche Sweep (ESS) Optimize Child Table Updates 100% 100% 100% 100% Green Green Green Green RC-6 Denormalized Views (removed from scope) RC-7 RC-8 RC-9 Histogram Test.Like Support READ/Reposition 100% 100% 100% Green Green Green 8
Asysco/Anubex Performance Enhancements Percent Complete Root Cause Status Description RC-10 Job/Spool/API Optimize 100% Green RC-11 RC-12 RC-13 RC-17 RC-19 Spool Purge 100% 100% 100% 100% 100% Green Green Green Green Green Optimize EXAMINE/TRANSLATE ASCII Translation Routines DISPLAY/WRITE Optimization General Ledger File Split 9
Go-live Weekend Activities Go-live planned to initiate November 18, 2022 1. Mainframe data unload 2. Data Migration 3. Reconfigure integrations 4. Technical health checks 5. Controlled business health checks 6. Transaction updates (any necessary daily cycles) 7. Full business health check 8. Leadership team go / no-go decision 10
Change Management Initiatives Five rounds of UAT have introduced many FAMIS users to the new system TrainTraq courses for significant changes in development for fall rollout New log on process Sort order difference System time out due to inactivity Continuing updates to project website Presentations to CFOs and CIOs Virtual Town Halls and connectivity validation planned for fall Site visits with several members completed Emails to CFOs with request to share broadly 11
Asysco Status All performance enhancements delivered, results are positive Focused on execution of tests for Shadow Server & AggieBuy Exploring further optimizations within the Monthly Payroll process Bi-weekly deliveries changing to monthly going forward Several workstreams are now complete with remaining workstreams close to completion excellent progress, strong effort across all teams We are shifting our efforts towards readiness Training Operationally Dress Rehearsal Cut-Over Planning
Asysco Summary Workstreams have been completed (or are very close) Everyone remains focused and positive We are in a really good place right now
AFR / OneStream Project Update 15
Annual Financial Report Update Progress on AFR project with EGP and OneStream continues Some challenges being resolved Project timeline has been re-structured Pilot project with a few members scheduled for August kick-off Provides more time for work on reports and processes Data load for FY 2021 complete and data validation in progress Data load for FY 2022 in progress 16