Guidelines for Polling Station Surveillance
"Learn about the measures to be taken for webcasting, CCTV coverage, and videography at polling stations, including camera positioning, presence of polling agents, signage requirements, and procedures for EVM and VVPAT handling. Ensure compliance with detailed instructions for transparent elections." (338 characters)
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Webcasting/CCTV coverage/videography, of polling station Following measures are to be taken: The position of the camera should be such that a broad view of the following aspects of elections (poll) proceeding are clearly captured and transmitted: i. Process of identification of voter by Polling Officer; ii. Application of indelible ink on the finger of voter; iii. Initialization of Control Unit of EVM by Presiding Officer after satisfactory identification of voter; iv. Voter's visit to Voting compartment for casting vote on the balloting unit of EVM, but without showing cover face of Ballot Unit so that voter's secrecy is preserved under all conditions;
v. Presence of Polling Agents to the possible extent; vi. At the time of closing of poll, distribution of slips to the voters in queue; vii. Sealing of EVM (BU/CU), VVPAT and giving copies of form 17-C to polling agents; d. The name and number of polling station along with date of poll should be pasted at such a place in the polling station so that the camera view will always display throughout. e. The Sector Officer concerned should give polling station- wise certificate to the Returning Officer that webcasting arrangements have been made as specified and are functioning properly.
Signage of size "30 inch by 18 inch" with colour scheme of black letters on fluorescent yellow Back ground, having the following text "YOU ARE UNDER WEB CAMERA/CCTV SURVIELLANCE". This signage shall be displayed prominently at multiple locations, inside and outside the polling booth. The name and number of polling station along with date of poll should be pasted at such a place so that the camera view will always display throughout.
Should be acquainted with the List along with phone no. of PHC/Hospitals/Nursing Homes adjacent to Polling Station. Polling Station having facility of Wheel Chair. Should be acquainted with a) Phone No. of Sector officer/Police Sector/HRFS/QRT, b) Phone No. of VAB.
Regarding EVM & VVPAT: Mock Poll shall be conducted 1Hr. before designated time of start of the Poll. PRO will wait for 15 min. if no agent or 1(ONE) agent is present. The Mock Poll shall be conducted with at least 50 votes and 1(ONE) vote at least for each candidate including NOTA.
Remove power pack (battery) after close of poll and before sealing of VVPAT in carrying cases in presence of Polling Agents handed over by Pro to RC counter and stored in Strong Room. A (polled), B (Polled defective) EVM machines will be Mock poll slips of VVPAT shall be kept in strong room. PRO shall be informed that plastic box containing separately. Each plastic box containing such slips must be labelled with AC no and PS no. Hence it should be handed over at RC counter
In polling station where number of voter is more than 1400, PS exceeds 1300 on the day time or if during the poll close time already 1300 voter have voted and there are 100 or more than 100 voter in the queue , Pro shall inform SO and accordingly SO must supply one VVPAT at such polling station maintaining all formalities In case on Poll day the voter turnout of that