LRC Architect RFP Award for Architectural & Engineering Services Update

measure b program update n.w
1 / 16
Embed
Share

"Learn about the latest update on the LRC Architect RFP award for architectural and engineering services. Details on the firms selected, interviews, and the final recommendation for the new Learning Resources Center design."

  • Update
  • Architectural
  • Engineering
  • Services
  • Learning Resources

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. MEASURE B PROGRAM UPDATE BOARD OF TRUSTEES WORKSHOP: AUGUST 20, 2019

  2. WORKSHOP for August 20, 2019

  3. Workshop: August 20, 2019 LRC Architect RFP Award for Architectural & Engineering Services Action Items Measure B Project Update

  4. LRC Architect RFP Award for Architectural & Engineering Services

  5. LRC Architect RFP Award for Architectural & Engineering Services The District issued an RFP for Architectural Design of the Learning Resources Center on February 15, 2019 for the Kentfield Campus. A Selection Committee made up of 16 members (4 classified staff, 4 faculty, 4 administrators, 2 students and 2 community members) was established. The following thirteen firms submitted proposals to the District for consideration on April 5, 2019: Perkins Eastman Dougherty Group 4 / HMC Carrier+Johnson / Cultur3 LCA Architects / Richard+Bauer DLR Group Kwan Henmi / Noll & Tam Architects LPA / Brick ELS / CambridgeSeven LPAS / Bohlin Cywinski Jackson gouldevans TLCD Architecture / Mark Cavagnero Associates HED WRNS Studio HGA

  6. LRC Architect RFP Award for Architectural & Engineering Services From the thirteen proposals received, the Selection Committee chose the following eight firms to move forward for interviews which took place on June 19, 2019: LPAS Perkins Eastman Dougherty TLCD / Mark Cavagnero Associates Group 4 / HMC Carrier+Johnson DLR Group Kwan Henmi WRNS Studio LPA / Brick

  7. LRC Architect RFP Award for Architectural & Engineering Services The Selection Committee asked Administration to consider the top two firms to move forward for additional follow-up questions and interaction with the senior executive staff of the District. The following two firms were selected to move on to a final interview which was held on July 25, 2019: LPA / Brick Group 4 / HMC Following a careful review by staff which included checking references for both shortlisted A&E teams, the Superintendent/President recommends the Board of Trustees award the contract for Architectural & Engineering Design Services for the Design of the new Learning Resources Center to Group 4 / HMC. Upon approval from the Board of Trustees, staff will proceed to work on a Professional A&E Design Services contract with District's legal counsel, Stradling, Yocca, Carlson and Rauth.

  8. BOARD ITEMS for August 20, 2019

  9. Board Items: August 20, 2019 LRC Architect RFP Award for Architectural & Engineering Services (K15-35712) - Award the contract for Architectural & Engineering Design Services for the Design of the new Learning Resources Center to Group 4 / HMC ADA Barrier Removal/Site Improvements (I25-35612) Project Assignment Amendment (PAA) Revision 01 SWA Group Jonas Center and Building 18 (I26-35610) Change Order 04 Alten Construction, Inc Building 27 (I47-35619) Deductive Change Order 01 Tiber Painting New Miwok Center (I51-35620) Revision 01 North Marin Water District Performing Arts (K03-35718) Deductive Change Order 01 Trahan Mechanical, Inc.

  10. Board Items: August 20, 2019 Fine Arts (K04-35719) Deductive Change Order 01 Paradigm General Contractors Athletic Synthetic Turf Fields and Restroom/Storage Facilities (K11-35715) Change Order 02 (Bleacher Fa ade) Robert A. Bothman Inc. PAA Revision 04 Verde Design, Inc Consent Items

  11. Project Update Report

  12. Project Update Report https://bmet.akennedygroup.net/tinyurl.aspx?k=2ea6f6ad48124

  13. LOOKING AHEAD

  14. Looking Ahead: September October 2019 Consent and Action Items Bond Quarterly Financial Update Renewal of Pools (MEP, Civil, Testing, Environmental, IOR) Property Acquisition (D60-35114) Change Order 01 Baja Mechanical, Inc. Jonas Center and Building 18 (I26-35610) Project Assignment Amendment (PAA) Revision 02 Geosphere Consultants Inc FF&E Purchase [VENDOR TBD] Maintenance & Operations Building and District Warehouse (K15-35712) PAA for Architectural Services (Student Store) [VENDOR TBD] FF&E Purchase [VENDOR TBD] Fusselman Hall (K14-35711) Construction Contract [VENDOR TBD]

  15. Looking Ahead: September October 2019 Consent and Action Items Bond Learning Resources Center (K15-35712) CEQA MND & Notice of Intent Swing Space (K19-35726) Construction Contract [VENDOR TBD] Design Build Contract [VENDOR TBD] Action Items Non-Bond Request for Proposal (KTD Housing)

  16. MEASURE B PROGRAM UPDATE BOARD OF TRUSTEES WORKSHOP: AUGUST 20, 2019