Michigan Interconnection Rules Strawman Overview - Fast Track Process Details
Explore the Michigan Interconnection Rules staff strawman overview, including details on the Rules Framework, Strawman Progress Definitions, and the Fast Track Process for interconnections of 20 kW and under. Learn about the initial and supplemental review screens, customer options, and the process flow from application to final approval.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Michigan Interconnection Rules Staff Strawman Overview Julie Baldwin Nicholas Evans July 16, 2019
Rules Framework Strawman title: Interconnection, Distributed Generation, and Legally Enforceable Obligation Standards Allotted R 460.901 through R 460.1101 Part 1. General Provisions Part 2. Interconnection Standards Part 3. Distributed Generation Standards Part 4. Legally Enforceable Obligation Standards
Strawman Progress Definitions Applicability Adoption of Standards by Reference Alternative Dispute Resolution Appointment of Experts Waivers Public Queue Interconnection Procedures Online Applications and Electronic Submission Communication Pre-Application Process Interconnection Application Modification Site Control Fast Track Process
Fast Track Process Overview Size eligibility still under review Matches FERC SGIP as currently written Initial screens Subset of screens applicable to 20 kW and under interconnections Potentially, additional screens may be added which are only applicable to 20 kW and under If the interconnection passes the screens Interconnection customer to pay good faith cost estimate (if any), proceed to installation, local government inspection, commissioning tests, interconnection agreement and final approval to operate Proceed to Facilities Study, if necessary
Fast Track Process Overview (cont.) If the interconnection fails any of the initial review screens Proceed to supplemental review screens Customer options meeting Proceed to supplemental review screens Move to study process Withdraw application
Fast Track Process Overview (cont.) Supplemental review screens Interconnection customer may specify the order of screens and pays actual costs of the review If the interconnection passes the supplemental screens Interconnection customer to pay good faith cost estimate (if any), proceed to installation, local government inspection, commissioning tests, interconnection agreement and final approval to operate Proceed to Facilities Study, if necessary
Fast Track Process Overview (cont.) If the interconnection fails the supplemental screens Proceed to study process Consider electric utility-recommended modifications, if any Withdraw application
Example Category 1 Timeline Processing Step Number of Days Application Received Electric Utility notifies interconnection customer of receipt Application Complete Notification within 10 business days Fast Track Initial Review Screens Review complete and interconnection customer notified within 20 business days Interconnection Customer notifies Electric Utility when project is installed and any required local code inspection and approval is complete Determined by interconnection customer Utility witnesses commissioning test and inspects site Not Specified Interconnection is approved and electric utility provides the interconnection agreement Within 5 business days of commissioning test and site inspection Electric Utility provides approval to operate To be determined
Queueing Do we want a separate queue for Category 1 and 2 projects (up to 150 kW)? Should Fast Track Initial Review, Fast Track Supplemental Review, and Study Process proceed in the same queue? Should the utility decide on a queue process and explain the mechanics in interconnection procedures?
Some remaining issues Procedures vs. Rules Use the term DER or something else (need to incorporate energy storage)? Are there too many timelines for reasonable tracking? More thought needed to determine the optimal number of days for each step. Need Michigan-specific adaptation of initial & supplemental review screens? Fast Track size eligibility Queueing
Next Steps Staff will email the first part of the strawman to the workgroup today Staff will present the remainder of the strawman at our final stakeholder meeting on August 28 Plan to request comments on the full strawman by a date in September (TBD) Another round of comments will be requested, if needed
Thank you! Questions?