Northstowe Phase 2 and 3 Update
Providing the latest updates on Northstowe Phase 2 and 3, Emma Brown shares insights and progress on making homes happen in the community. Stay informed about the developments and upcoming opportunities in this exciting project.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Making homes happen Northstowe Phase 2 and 3 Update Emma Brown
Central One Update Homes England Phase 2b Keepmoat #MakingHomesHappen 2
Central One Northstowe Town Centre #MakingHomesHappen 3
Market Hall Convenience Store Space for Civic Hub (library/health/community space) Town gardens Play area Residential Units #MakingHomesHappen 4
Central One - Programme Developer has been selected Sept. 2022 Homes England to announce development partner in January 2023 Development Partner to submit Reserved Matters planning application submission early 2023 Construction starts late 2023 Central One Complete early 2027 #MakingHomesHappen 6
Phase 2B - Keepmoat #MakingHomesHappen 7
Phase 2b Keepmoat (300 homes) #MakingHomesHappen 8