October 2017 Manufacturing and Control Updates for Teleconference ACS FREIA

teleconference acs freia 31st october 2017 n.w
1 / 7
Embed
Share

Stay updated on the manufacturing progress including cryostat and liquid insert developments, as well as control system design updates in the October 2017 teleconference agenda for ACS FREIA.

  • Manufacturing
  • Control
  • Teleconference
  • Updates
  • October

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Teleconference ACS FREIA 31st October 2017 Agenda: Manufacturing follow-up Control and command follow-up Planning Commissioning test organization

  2. Manufacturing follow-up Cryostat Dewar piping completed with insulation (W43) Thermal shield : cooling pipes validated (He leak test and thermal shock), welding ongoing (W?) Instrumentation and wiring ongoing (started W43) Technergie visit planned Tuesday to install the junction box (W44) Magnet insert Manufacturing drawings reviewed (26thOctober) Top lid (starting part) is under plasma cutting Issue to keep the tolerances after delivery to the subcontractor so send for water jet cutting instead Current lead equipment (flowmeters, heaters, sensors) to be defined by ACS Need date on the pressure drop for the current lead cooling Heat exchanger HX683 welding design presented and validated by CD and ACS Manufacturing start in W44 31/10/2017 Teleconf ACS - FREIA 31st October 2017 2

  3. Manufacturing follow-up Liquid insert Waiting for final cabling Insertion inside the cryostat in W44 Valve box Piping done, test ongoing to find and repair any leak before closure (W44) Leak found on the top thermal screen repaired but not confirmed Heaters and thermometers set on the thermal shield, 4k pot and heat exchanger Cernox installation ongoing 31/10/2017 Teleconf ACS - FREIA 31st October 2017 3

  4. Manufacturing follow-up Transfer lines Manufacturing of the single line and multiline under way Simulator box Manufacturing drawings reviewed, translation to be checked before sending Manufacturing started W43 31/10/2017 Teleconf ACS - FREIA 31st October 2017 4

  5. Control and Command follow-up Control system design Programming done, waiting for test with GERSEMI systems Control system procurement Junction boxes done Missing connectors BURNDY male 19 pins, to be send by UU Electrical cabinet delivered at CD Cabling of the VB to the cabinet in W44 Cabling of the VC to the cabinet in W45 Cables cut after installation on dummy trays, reproducing the laboratory FREIA infrastructure 31/10/2017 Teleconf ACS - FREIA 31st October 2017 5

  6. Planning: GERSEMI 2017 2018 October 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 November December January February March April junction box manufacturing VB electrical wiring, closure and test Liquid insert electrical wiring VC electrical wiring and test Simulator manufacturing and test Simulator electrical wiring Magnet insert manufacturing Magnet insert wiring Electrical cabinet delivery Final electrical wiring of control cabinet & test Control cabinet & automaton test - Factory acceptance test with VC - Factory acceptance test with simulator Control cabinet & automaton test with magnet insert Shipping of the vertical cryostat and liquid insert Shipping of the valve box and simulator Installation of project onsite Cryogenic tests with simulator Final installation of project without simulator Acceptance tests with liquid insert Acceptance tests with magnet insert 31/10/2017 Teleconf ACS - FREIA 31st October 2017 6

  7. Commissioning test organization Preliminary tests Final assembly tests: Leak tests pipes and valves Commissioning tests Week 47-48: wiring check VC and liquid insert Week 49: sequence tests with automaton and VC (22,23,25) Week 50-51: sequence tests with automaton and simulator (1,3,5,8,9,10,12,14,21,23) 31/10/2017 Teleconf ACS - FREIA 31st October 2017 7

Related


More Related Content