Perspectives on Offshore Renewable Energy Consenting

Perspectives on Offshore Renewable Energy Consenting
Slide Note
Embed
Share

Delve into the insights shared at the 9th MRIA Marine Renewables Emerging Technologies Industry Forum by Danielle Conaghan, Partner at Arthur Cox on 2nd February 2018. Explore the complexities and considerations surrounding offshore renewable energy consenting and gain valuable perspectives on this evolving industry sector.

  • Energy
  • Renewables
  • Offshore
  • Industry
  • Forum

Uploaded on Feb 16, 2025 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Perspectives on offshore renewable energy consenting 9th MRIA Marine Renewables Emerging Technologies Industry Forum Danielle Conaghan, Partner, Arthur Cox 2 February 2018

  2. 5 Lessons (in the process of being) learned! 1. Marine Spatial Plan can consents be given without it? 2. Applications what s the actual reality of your project? 3. Grid connection is the O Grianna fallout over yet? 4. Are extensions to the life of a planning consent still possible? 5. Is there still latitude for immaterial deviations? 2 |

  3. 1. Marine Spatial Policy Marine spatial plans ETA 2021 Decisions should not be delayed in anticipation of adoption of plans. Maighne Case Highfield Solar Case 3 |

  4. 2. What is the actual reality of your project? An Taisce v An Bord Plean la (Edenderry Case) Indirect effects on the environment of extraction of peat fuel source Application must include direct and indirect effects of your project 4 |

  5. 3. Grid Connection O Grianna Case functional interdependence Daly v Kilronan Case - exempted development not available if EIA / AA required S. 5 declarations Sweetman v An Bord Plean la (Grousemount) Case 5 |

  6. 4. Extensions to duration of consents Current Law 1 extension only for 5 years only. Two different tests to be satisfied: Substantial works Test or Economic / Technical Reasons Test Proposed change of law no more extensions if EIA and / or AA were required before permission was granted (S. 28 Planning and Development (Housing) and Residential Tenancies Act 2016.) 6 |

  7. 5. Immaterial deviations Still allowed but exercise caution. Many exceptions apply (e.g.): Consent says strictly Significant effect on environment / habitats / significant disturbance of species Kilvinane Case substitute consent process Strategic Capital Case no immaterial deviations for exempted development 7 |

  8. Thank you for your time today. Danielle Conaghan, Partner, Environment and Planning, Arthur Cox Danielle.conaghan@arthurcox.com + 353 1 920 1082 2 February 2018