Preparation for CM Hardware and Software Upgrades

Preparation for CM Hardware and Software Upgrades
Slide Note
Embed
Share

This content outlines the preparation activities for series CM hardware including RF stations, sensors, gauges, doorknob vacuum pumping, and software upgrades. It details tasks such as installation, testing, validation, and documentation before and after the CM arrival. The to-do lists assign responsibilities to team members for tasks like power supply installation, station testing, software validation, cryogenic procedures, and sensor calibration. Images provided visually showcase the equipment and stations involved in the preparation process.

  • CM hardware
  • software upgrades
  • preparation
  • RF stations
  • to-do list

Uploaded on Feb 18, 2025 | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Preparation for Series CM Hardware: RF stations Doorknob Vacuum pumping cart Sensors and gauges: arc detector, electron pickup Necessary cable pulling/ terminal box/cable naming/numbering Test box Cryogenic jumper

  2. Preparation for Series CM RF station: ElEctrosy: We got back of the G1 power supply and installed in the HPA1. Also, related modification has been down for HPA2.

  3. Preparation for Series CM RF station: DB station: RF power test up to 400 kW (measured internally) & about 360 kW (measure at the load) Observation: Water conductivity issue in section A PLC disconnection Uncertainty of Ia and Ig1 meter

  4. Preparation for Series CM Software: LLRF upgrade LLRF2 has successfully upgraded PID mode of LLRF2 is under testing

  5. To do list Before CM arrival: number item Person in charge status 1 Get back and install G1 power supply for Electrosys Rolf, Tord close 2 Test DB and Electrosys station to full power Rolf, Tord, Han, Michael On going 2 Ask for shock senor reader preparation, test box, documentation Roger opening 3 Tuner control software validation Kjell opening 4 Dismount of doorknob Lars opening 5 Validation of vacuum pumping cart Lars On going 6 Overall check with the LLRF/software Han, Tor, Kjell opening 7 Cryogenic procedure Lars, Esat opening 8 Test documentation Han close

  6. To do list After CM arrival: number item Person in charge 1 Akira, Han Readout information of shock sensor and vacuum 2 Han, Akira Visual checking of CM 3 Cavity frequency at room temperature Han 4 Sensor/cable continuity (test box) Akira 5 Lars FPC and doorknob installation 6 Lars Vacuum pumping system installation 7 Calibration of the pressure sensors/MKS Konrad