This presentation outlines the Proposed S.R.26 Pavement Replacement Project scheduled for Thursday, December 13, 2012, at 6:00 p.m. at East Jay Middle School in Portland. It covers the public hearing format, sign-in procedures, project stakeholders, development process, and environmental document requirements under NEPA.
Download Presentation
Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Proposed S.R. 26 Pavement Replacement Project Thursday, December 13, 2012 6:00 p.m. Presentation East Jay Middle School 225 East Water Street in Portland
Welcome Rickie Clark, INDOT Office of Public Involvement Purpose/Explanation of Public Hearing Public Hearing Format Visit our sign-in table Informational Handouts Submitting public comments for hearings transcript Project display area
Public Hearing Sign-in at attendance table to be added to project mailing list A public hearing notice was mailed to known property owners within project area Announcement of this hearing was posted to INDOT website. A media release was also issued Legal notice of public hearing published in the Commercial Review (Portland) on 11/28/12 & 12/5/12
Project Team Introduction of INDOT Project Officials Project Management Design Real Estate Public Involvement City of Portland Jay County Recognition of Elected Public Officials
Project Stakeholders Indiana Department of Transportation Indiana Division Federal Highways Administration Jay County City of Portland Local communities Elected Public Officials Community residents and citizens Commuters Trucking industry Schools Emergency Services
Project Development Process Project purpose & need develop project alternatives Engineering Assessment Screen project alternatives Release environmental document & preliminary design Public Hearing to solicit public comment 2012 Additional work on project alternatives & preliminary design Right-of-Way Construction We Are Here
Environmental Document Requirement of the National Environmental Policy Act (NEPA) Requires INDOT to analyze and evaluate the impacts of a proposed project to the natural and socio-economic environments Impacts are described in environmental document Environmental document was released for public involvement November 2012
Environmental Document Development of document begins once purpose and need for the project has been clearly identified Develop a number of possible alternatives including a Do Nothing alternative as a baseline for comparison Screen alternatives to identify a preferred alternative Solicit public comment on environmental document and preliminary design plan Solicit, address, and fully consider public comments as part of decision making process
Elements of the Environmental Documentation Real Estate Air Quality Noise Farmland Hazardous Materials Historic/Archaeological Cultural Resources Community Impacts Wetlands and Waterways Floodplains Endangered Species
Environmental Document Jay County Public Library, 315 North Ship Street, Portland, Indiana 47371, (260) 726-7890 INDOT Greenfield District Office, Planning & Programming Department, 32 South Broadway, Greenfield, Indiana (855)-463-6848 INDOT Office of Public Involvement, Indiana Government Center North, Room N642, 100 North Senate Avenue, Indianapolis (317) 232-6601
Purpose and Need Improve roadway to meet geometric requirements Provide pedestrians with adequate and safe sidewalks Increase capacity of the storm drainage system Improve condition of pavement, curb & sidewalk Enhance safety within the corridor
Proposed Improvement Improved radii at intersections and driveways New sidewalks and curb ramps that meet ADA (American Disability Act) compliance Improved Drainage Updated storm sewer system, which includes new curb and gutter New pavement under-drains New signage Updated crosswalk markings at school locations
Proposed Improvement Two 11-foot wide travel lanes 1.5 foot wide curb & gutter 3 foot wide grass buffer strip 4 foot wide sidewalks on both sides of roadway Install new sewer line Along Garfield Street from S.R. 26 south through city maintenance area Weiler-Wilson Park to Salomonie River where new outfall will be installed
Proposed Improvements Full depth pavement replacement.
Proposed Improvement Weiler-Wilson Park to Salamonie River Section 4(f) property (publicly-owned recreational area) New sewer line to go south through grass-covered area between 2 baseball fields at park to the river Following installation of sewer line, the park will be restored to its current condition Sewer installation will have no permanent impact on the park Project will not adversely impact activities, features or attributes of the park
Maintenance of Traffic (MOT) Official detour will utilize U.S. 27, S.R. 67 and Ohio S.R. 49 Driveways will remain open for homeowners who require access from S.R. 26
Real Estate Acquisition Residential Public Park Permanent R/W 0.3 Acre 0.4 Acre 0.7 Acre Permanent R/W estimates based on information available at this time An additional 0.6 acre of temporary r/w is required
Real Estate Acquisition Process "Uniform Act of 1970" All federal, state, and local governments must comply Requires an offer for just compensation Acquisition Process Appraisals Review Appraisals Negotiations
Project Schedule Public Hearing December 2012 Environmental Document Finalized: Early 2013 Preliminary Design Plan refinement: Early 2013 Real Estate Acquisition Activities: Spring 2013 Appraising Negotiations / Buying Utilities coordination / relocation Project Let for bidding: 2014 Construction: 2014 - 2015
INDOT would like to hear from you Talk with INDOT project team members Comment sheet in information packet E-mail or Mail comments to INDOT Sign-in sheet to be added to project mailing list Visit INDOT website at www.in.gov/indot/2366.htm Public Involvement page All comments are very much appreciated and will be given full consideration by project team
Public Involvement Team Rickie Clark, INDOT Office of Public Involvement (317) 232-6601 rclark@indot.in.gov Katie Hilderbrand, Greenfield District Customer Service Manager, (855) 463-6848 khilderbrand@indot.in.gov Harry Maginity, Greenfield District Media Relations Director, (855) 463-6848 hmaginity@indot.in.gov
Project Resource Location Greenfield District Office, 32 South Broadway, Greenfield, Indiana 46140 Responsible for transportation construction, maintenance and development activities in East Central Indiana eastcentralin@indot.in.gov (855) 463-6848 Brandye Hendrickson, District Deputy Commissioner Katie Hilderbrand, Customer Service Manager Harry Maginity, Media Relations Director
Submit Public Comments Submit public comments using the options described in 1st page of information packet Public Comment Form Via e-mail Participating during public comment session via microphone Verbal comments recorded and transcribed for inclusion into to public hearings transcript INDOT respectfully requests comments be submitted by Monday, January 7, 2013 All comments submitted will become part of public record, entered into transcript, reviewed, evaluated and given full consideration during decision making process
THANK YOU Please visit with INDOT project officials following the public comment session Project Open House Project maps, displays, real estate acquisition table, INDOT project officials, informal Q & A Thank you for your attendance this evening