
Resource Integration and Stability Assessment Updates for Power Grids
The provided content covers various updates and plans related to resource integration and stability assessments within the power grid domain. It includes details on converting ESR data, synchronization dates, quarterly stability assessments, and model quality tests. The updates aim to ensure efficient operations and reliable performance of power generation resources.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Resource Integration Topics Jenifer Fernandes ERCOT Resource Integration Working Group October 24, 2024
Grid Interconnection Organization Updates Kenisha Webber: Large Gen Supervisor John Lawson: Small Gen Supervisor 2
RIOO Update ESR conversion Plan for collecting new ESR information, converting combo models, and final cleanup of data ESRs with PLDs on or prior to Sep. 2024 o Done - RFI information collected via DocuSign ESRs with PLDs of 10/2 and 11/1 o Modeling to send RFI template to directly to AR and BAR of ESR Completed spreadsheet should be submitted as an attachment-only RSCR o Convert to single model via script with RFI data. o Deadline to submit the RFI data in RIOO-RS is 12/2/2024. ESRs with PLDs of 12/4, 1/8, and 2/5 o Resource Integration to provide RFI template to RE. Completed spreadsheet should be submitted with the INR in RIOO-IS o After graduation, convert to single model via script with RFI data o Deadline to submit the RFI data in RIOO-IS is 12/2/2024. All in-flight ESR with 3/5 after or without PLD converted in RIOO-IS: o Within IS, run script to convert to single model o RE to provide all required data via RIOO panels Note: Providing good quality data is necessary to efficiently convert from Combo Model to Single Model. 3
Quarterly Stability Assessment (QSA) Planning Guide 5.3.5 Next Deadline for QSA All-Inclusive Generation Resource Initial Synchronization Date Upcoming January, February, March Last Day for an IE to meet prerequisites as listed in paragraph (4) below Prior August 1 Completion of Quarterly Stability Assessment End of October Prior November 1 End of January Upcoming April, May, June Prior February 1 End of April Upcoming July, August, September Prior May 1 End of July Upcoming October, November, December If a GINR is not included in QSA, its Initial Synchronization date will be automatically delayed to the next quarter 4
Quarterly Stability Assessment (QSA) Planning Guide 5.3.5, Quarterly Stability Assessment Issue s seen in previous QSA s 10 day comment period for FIS Needs to be complete before QSA deadline TSPs need to plan for it Dynamic/PSCAD Model Review Dependent on FIS Stability study Need to meet PG 6.9 15 to 30 days prior to QSA deadline PSSE Model Quality Test Required PSCAD Model Quality Test, Unit Model Validation and Template is required. PSCAD template is required starting August 1st QSA. TSAT Model Required If PSSE model is UDM, then TSAT model should be UDM and should include MQT 5
PGRR112: Feb 1,2025 QSA implementation FIS studies finalized and posted in RIOO-IS 45 days prior to quarterly stability assessment deadline. Dynamic models (PSEE, PSCAD, TSAT (UDM)) and MQT report submitted in RIOO-IS. From Planning guide Section 5.3.5 (2): Last Day for an IE to meet prerequisites as listed in paragraph (4) below Prior August 1 45 day deadline June 17 Prior November 1 September 17 Prior February 1 December 18 Prior May 1 March 17 6
PGRR088- Include Financial Security Amount in RIOO-IS RIOO-IS implementation 12/11/2024 Planning guide 5.2.8.1 (5): 5) Within ten Business Days of providing the TSP both the notice to proceed with construction of the interconnection for the Generation Resource and the financial security sufficient to fund the interconnection facilities pursuant to the SGIA, the IE must submit a change request via the online RIOO system to provide the financial security amount if it is not redacted in the public version of the SGIA filed with the Public Utility Commission of Texas (PUCT). ERCOT will include in the monthly Generator Interconnection Status report the name of the interconnecting TSP and the total amount of financial security sufficient to fund the interconnection facilities, if provided by the IE. 7
PGRR094: Requirement for Generator Construction Commencement or Completion Implemented in RIOO-IS. IE/RE can add submit or update the Construction Start and End Date via Change Request in RIOO-IS. Construction Start Date Enter (1) the date that physical on-site work of a significant nature (such as footing excavation or concrete pouring for foundations) has begun and is on-going, or (2) the date that major equipment items have been delivered to the site. Physical work of a significant nature does not include preliminary activities such as surveying, site clearing, test drilling and decommissioning of existing facilities. Construction End Date Enter the date when all plant systems are ready for commissioning/starting activities. 8
Commissioning Requests Submission- New Email Address ERCOT has established a new, dedicated email address for Market Participants to submit new generator Commissioning Checklist for review. Starting June 10, 2024, all new Commissioning Checklists (Parts 1-3) should be emailed to CommissioningRequests@ercot.com in addition to being submitted to RIOO-IS. Commissioning Checklists (Parts 1-3) submitted to ResourceIntegrationDepartment@ercot.com after June 21, 2024, will not be processed. Commissioning Plans should not be emailed for review to the new Commissioning Request email address. 9
Generation Interconnection Requests 1,881 active generation interconnection requests totaling 372 GW as of September 30th, 2024 (Solar 154 GW, Wind 35 GW, Gas 26 GW, and Battery 154 GW) (Excludes capacity associated with projects designated as Inactive per Planning Guide Section 5.7.6) 10
Generation Interconnection Requests Small Gen- 29 projects Not Model Ready, 48 projects Model Ready 11
Other contact information ResourceIntegrationDepartment@ercot.com is distribution list for Resource Integration department Mailing List RESOURCE_INTEGRATION@LISTS.ERCOT.COM 12
Questions? Thank you!
Current Process for Large Generation Project Wanting Simultaneous Screening Study and Full Interconnection Study (No Construction Bottleneck) 20 Months Assumptions IE submits correct data IE meets all milestones IE does not change equipment TSP has no backlog 6/21/2020 Part 1 Approval 2/1/2020 QSA Deadline 5/1/2020 QSA Complete 7/1/2020 Part 2 Approval Earliest Sync Based on QSA 7/1/2019 Reactive Study 4/1/2019 SS Complete 1/1/2019 6/1/2020 PLD* INR Request Initiated 9/1/2020 Part 3 Approval 1/1/2019 9/1/2020 TSP Complete FIS (10 months) Range 9 to 13 months Kick-Off -2 weeks Sign Study Scope months Received Payment 1 month SS Study months SC month Dynamic months Facility months ERCOT Approved 11/1/2019 - 2/1/2020 2/1/2020 - 6/1/2020 SGIA, NTP & Financial Commitment Days RARF Submission 7/1/2020 - 9/1/2020 2/1/2020 - 7/1/2020 Testing ~5 months SSR Study Completed and Approved *Interim updates are not allowed for new units. Interim update requests must be approved by ERCOT Network Modeling. Construction time for TSP to construct needed facilities not shown. Start of construction dependent on RE giving TSP Notice to Proceed and providing the Funding to construct the interconnection facilities. Length of time needed for construction depends on facilities being constructed. The PLD shown above is normally after completion of construction. 14
New Process for Small Generators TDSP Work Prior to RIOO Submittal (8 to 10 Months Timeline for Projects After the DGR Moratorium) 5/19/2022 Part 1 Approval 1/14/2022 Review required Submissions 1/31/2022 Registration RARF Approval 10/3/2021 Optional Small Gen Review Meeting 1/18/2022 Review RARF 5/31/2022 Part 2 Approval 1/4/2022 5/4/2022 PLD* 7/31/2022 Part 3 Approval Submit INR in RIOO 10/1/2021 8/1/2022 5/4/2022 - 7/31/2022 2/1/2022 - 5/1/2022 10/1/2021 - 1/1/2022 Commissioning Checklists & Testing Days RARF Submission (Prior to PLD) IE/RE Work with TDSP (IA, System Impact Studies, Interconnection Requirements, Operational Limitations, ETC) *Interim updates are not allowed for new units. Interim update requests must be approved by ERCOT Network Modeling. Construction time for TSP/DSP to construct needed facilities not shown. Start of construction dependent on RE giving TSP Notice to Proceed and providing the Funding to construct the interconnection facilities. Length of time needed for construction depends on facilities being constructed. The PLD shown above is normally after completion of construction. RE should have all TSP/DSP studies and IA complete before requesting the scoping meeting. 15
New Process for Small Generators RIOO Submittal Prior to TDSP Work (8 to 10 Months Timeline for Projects after DGR Moratorium) 8/27/2022 Part 1 Approval 4/30/2022 Registration RARF Approval 4/1/2022 1/9/2022 Optional Small Gen Review Meeting Submit required Submissions 4/14/2022 Review required Submissions 9/5/2022 Part 2 Approval 1/4/2022 8/3/2022 PLD* 4/18/2022 Review RARF Submit INR in RIOO 10/31/2022 Part 3 Approval 1/4/2022 11/1/2022 1/4/2022 - 4/1/2022 8/3/2022 - 11/1/2022 5/1/2022 - 8/1/2022 IE/RE Work with TDSP Commissioning Checklists & Testing Days RARF Submission (Prior to PLD) IE/RE Work with TDSP (IA, System Impact Studies, Interconnection Requirements, Operational Limitations, ETC) *Interim updates are not allowed for new units. Interim update requests must be approved by ERCOT Network Modeling. Construction time for TSP/DSP to construct needed facilities not shown. Start of construction dependent on RE giving TSP Notice to Proceed and providing the Funding to construct the interconnection facilities. Length of time needed for construction depends on facilities being constructed. The PLD shown above is normally after completion of construction. RE should have all TSP/DSP studies and IA complete before requesting the scoping meeting. 16