Smart Meter Texas Update and Integration Progress

lubbock integration update rms april 2025 n.w
1 / 4
Embed
Share

Stay updated on the progress of Smart Meter Texas integration and RMS updates for April 2025. Get insights on discretionary fees remediation and expectations for market go-live dates. Ensure you provide the necessary information for check disbursement from each CR. Explore the latest developments and timelines in the smart meter Texas project.

  • Smart Meter Texas
  • Integration
  • RMS Update
  • Discretionary Fees
  • Market Go-Live

Uploaded on | 24 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. LUBBOCK INTEGRATION UPDATE RMS APRIL 2025

  2. DISCRETIONARY FEES REMEDIATION We are getting to the final stages for a few of the REPs. We walked through the process yesterday to get the first check cut for one REP. We are expecting an update to see how long it actually takes the check to get cut and sent. WHAT WE NEED FROM EACH CR We need an address that you want the check sent to. Your REP Account manager has been trying to get ahold of you. If you haven t seen an email, please email MarketOps@mylubbock.us If you want the check to sent Care of anybody, give us that name as well.

  3. SMART METER TEXAS March 31 April 4 Setting up and testing connectivity. April 3 May 14 Testing May 20 Technical GO LIVE Market Notice and begin sending Data June 17 Market GO LIVE

  4. SMART METER TEXAS EXPECTATIONS We are sending a full sync each day. There is a 1-day delay for the data (similar to us sending LSE data to ERCOT) Monday s Data (closing out 12am Tuesday) will be sent to SMT late Tuesday/Early Wednesday Morning