SQAS 2.0 Development Project Overview
"Get insights into the development phases of the SQAS 2.0 system, aimed at enhancing user-friendliness and functionality. Follow the timeline, methodology, and key collaborators involved in this innovative project."
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
The new SQAS website: SQAS 2.0 29-9-2022 Giulia Casasole, Cefic Project Manager
SQAS 2.0 SQAS 2.0 Re-develop the SQAS system to make it more user friendly and effective for all its users and expand its overall use. The re-development concerns the functionalities of the SQAS system and not the content of the SQAS questionnaires. Page 2
What was already done April-June 2021 September-November 2021 November-December 2021 May 2022 January-March 2022 April 2022 Start of the development Signature of the contract Selection of the supplier Brainstorming with all types of users Tender Drafted the terms of reference Deloitte Megabyte Pharox NRB NSI Easi Decide which additional functionalities are needed in the new system (in addition to the current functionalities) Describing the new system and included all feedback given in the brainstorming sessions Page 3
Reminder: Methodology to develop SQAS 2.0 A two-stage approach: 1. Co-Design Phase aiming to design the detailed infrastructure, to align Cefic s Experts proposals with technical capabilities and associated costs. Outcome: Scope document that describes in detail the system. 2. Technical implementation stage in which the system is developed This stage includes also testing phases to check that the system works before its launch in May 2023. Involved a team of experienced users in both stages Page 4
Experienced users involved in co-design and development stages Chemical companies A. Delzenne: Solvay Anna Beliaeva: BASF M. Migne: TOTAL E. Neumann: Dow W. Rubens: ExxonMobil S. Beddegenoodts: SABIC Logistics industry/Distributors G. Ahlbrecht: FECC E. Spaanderman: Panalon M. Vetter: Bertschi E. Seliaerts: EFTCO E. de Jong: ECTA Assessors F. Sanchez & I. Bots Page 5
Co-design phase Timeline: May-September 2022 Meetings: 6 meetings of Cefic team (V. Trapani, G. Casasole, J. Naessens and IT expert) with Easi team 1 confcall and 2 online workshops with the Experienced users Outcome: Scope document (about to approve it) Page 6
Development phase Timeline: September 2022-April 2023 (Launch of the platform expected for May 2023) Organized in 3 sprints (in each sprint a part of the platform is developed), followed by testing phases September-November April May February-March November-February 3 sprint 2 sprint 1 sprint Launch of SQAS 2.0 Trainings Testingby 50 users Testing by Cefic Testing by Cefic & Experienced users Testing by Cefic & Experienced users Call for volunteers: We need your help! Page 7
Thank you! If you have any questions, you can contact me at gca@cefic.be