Summary of Run-14 RHIC Machine Experiments Meeting - July 31, 2014
The summary slides from the Run-14 RHIC Machine Experiments Meeting held on July 31, 2014, cover various activities such as cool-down processes, beam injections, physics setups, and operational timelines from February to July. They also detail the concurrent operations with RHIC setup, luminosity projections, and milestones achieved in the FY2014 program. Get insights into cryogenic operations, research initiatives, and collider projections for FY2014-2018.
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Run 14 RHIC Machine/Experiments Meeting 31 July 2014 Summary Slides 1
Run 14 as run 3 Feb, Begin cool-down to 4.5K 4 Feb, Cool-down to 6K in Blue 7 Feb, Blue and Yellow at 4.5 deg K 10-Feb, Beam in Blue and Yellow at injection 15-Feb, Begin s = 14.6 GeV/n AuAu physics 11 Mar (Tuesday, 0800), End s = 14.6 GeV/n AuAu physics run begin setup for s = 200 GeV/n AuAu 15-Mar (~14:00, store 18046), Begin s = 200 GeV/n AuAu physics run PHENIX 1st physics store = 18046 (15 March) STAR 1st physics store = 18064 (17 March) 16-Jun (0700), end 13.3 week s = 200 GeV/n AuAu run 16-June begin setup for s = 200 GeV/n 3HeAu run 20-June first Physics Store 6-July (0700), end 2.3 week s = 200 GeV/n 3HeAu run, power supply regulator work 7-July, Test DX move then begin cryo warm-up 10-July, warm-up complete, 22.4 cryo weeks of operation 2
http://www.bnl.gov/cad/esfd C-A Operations-FY14 30 Sep 14 Scheduling Physicist: Chuyu Liu as run concurrent with RHIC setup with beams ramp up luminosity FY 2014 Program Element Sep Oct Nov Dec Jan Feb Mar Jun Aug Sep Apr May Jul AGS-Booster-Tandem/Linac/EBIS Startup 22 weeks 4 July RHIC Cryo Cooldown to 45 deg K RHIC Cryo Cooldown/Warm-up 3 Feb RHIC Cryo Operation RHIC Cryo off 16 weeks RHIC STAR & PHENIX 15 Feb setup as required 13.3 weeks RHIC Research with s = 200 GeV/n AuAu 3 wks 10 Mar RHIC Research with s = 15 GeV/n AuAu RHIC Research with s = 200 GeV/n 3HeAu .4 weeks 5.5 weeks RHIC Development - Test DX Move 27 May 7 Oct 16 May 15 Nov 20 Jun 31 Mar 25 Mar 14B NSRL (NASA Radiobiology) 14A 13C 29 Mar 7-8 Jun NSRL (NRO) 22 Nov 18 Nov BLIP (Isotopes) 17 Dec 31 Jul BLIP (other) Shutdown (RHIC) 3
Through final fill 18010, 11 Mar 2015 max/min projections from Fischer et.al. RHIC Collider Projections (FY2014-FY2018) , 4 June 2013 From Ingrassia, http://www.cadops.bnl.gov/AGS/Operations/Run14/ 4
? 6
(last 3 days) Max projection 11 Fischer et. al. RHIC Collider Projections (FY 2014 FY 2018) , 4 June 2013