ERCOT Outage Study Cases in System Operations Test Environment (SOTE)

scr799 ercot outage study cases in the system n.w
1 / 5
Embed
Share

Explore how ERCOT provides outage study cases in the System Operations Test Environment (SOTE) for Transmission Service Providers (TSPs) to enhance outage evaluation and approval processes, improving grid reliability.

  • ERCOT
  • Outage Study
  • System Operations
  • Transmission Service Providers
  • Grid Reliability

Uploaded on | 0 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. SCR799 ERCOT Outage Study Cases in the System Operations Test Environment (SOTE) Yugendher Karedla September 26, 2024

  2. SCR799 - ERCOT Outage Study Cases in the System Operations Test Environment (SOTE) The System Operations Test Environment (SOTE) is an environment of the ERCOT Energy Management System (EMS) where the Network Operations Model and the results of the Real-Time State Estimator (SE) are available for review and analysis within five minutes of the Real-Time solution. This environment is provided as a platform for Transmission Service Providers (TSPs) to perform power flow studies, contingency analyses and validation of SE results. SCR799 enables ERCOT to provide Current month s- 60 day and 90 day outage study cases in SOTE for TSPs on monthly basis. Providing access to these ERCOT outage cases in SOTE improves the ability of TSPs to evaluate outages prior to submittal to ERCOT, there by increasing the likelihood of outage approvals by ERCOT. Project Status: In execution phase. 2 PUBLIC

  3. SOTE Current State 3 PUBLIC

  4. SOTE Future State (Post SCR799) Functionality highlighted in green text are currently available in SOTE TOs 60 Day EMS WebFg Future SOTE EMS 90 Day EMS WebFg Real-Time One Lines 60 Days One Lines 90 Days One Lines ERCOT Citrix Gateway Real-Time Case 60 Days Ahead Case 90 Days Ahead Case Dynamic Ratings Real-Time Up to 7 Days > 7 Days Import Custom Resource & Load Plans, Breaker Status Schedules Load Outages Current Day Future Day Forecast Next 7 days Cases Include Contingency Definitions RAS/RAP Load Distribution Factors DPCs if applicable 4 PUBLIC

  5. Project activities and milestones Completed Design Completed Environment Readiness 09/04 SOTE with 60/90-day outage study cases for the month of September are available. Testing 09/10 10/01 Market Notification with Training Documentation 09/26 Enhanced SOTE will be live 10/09. Go Live 10/09 5 PUBLIC