ERCOT Regional Transmission Planning Cascading Outage Analysis

overview of rtp cascading outage analysis n.w
1 / 14
Embed
Share

System operators like ERCOT conduct detailed analysis to prevent cascading outages that can result in widespread service interruptions. This involves studying various contingency events, performing cascade analysis on base and sensitivity cases, and evaluating potential actions for extreme events in line with NERC requirements. The analysis includes examining specific NERC contingencies, such as faults, relay failures, and system adjustments, to ensure system reliability and performance under different peak and off-peak scenarios. Understanding the cascading analysis methodology helps in enhancing grid resilience and planning for future system conditions.

  • ERCOT
  • Cascading Outage
  • Transmission Planning
  • NERC Requirement
  • Grid Resilience

Uploaded on | 1 Views


Download Presentation

Please find below an Image/Link to download the presentation.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.

You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.

The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.

E N D

Presentation Transcript


  1. Overview of RTP Cascading Outage Analysis Yong Cheng Transmission Planning Assessment

  2. ERCOT - Regional Transmission Planning (Planning Assessment for 2 to 6 Year Future System Conditions) Other Reliability Studies Case Building Sensitivity analysis Short circuit study Initial start cases, and contingency list ready Long-lead time equipment study Report and Posting Multiple element outage and cascading analysis Set 1 (P1, P7), Set 2 (P2, P4, P5) contingency analysis for the base cases Set 3 (P3: G-1+N-1, part of P6: X-1+N-1) contingency analysis for the base cases Economic case preparation and analysis 2 PUBLIC

  3. System Cascading NERC Requirement Definition in NERC s Glossary of Terms The uncontrolled successive loss of system elements triggered by an incident at any location. Cascading results in widespread electric service interruption that cannot be restrained from sequentially spreading beyond an area predetermined by studies. Requirements in NERC TPL-001-4 (Transmission System Planning Performance Requirement) - Table Steady State & Stability Performance Planning Events of the TPL does not allow any cascading under Planning events (P1 through P7) - R3.5 and R4.5 requires evaluation of possible actions for potential cascading caused by extreme events 3 PUBLIC

  4. Cascade analysis in RTP Any contingency event defined in the TPL-001-4 standards where a non-consequential load shed is an acceptable corrective action plan will be screened further for potential cascade conditions ERCOT performs the initial screen as well as detailed cascade analysis This analysis is conducted on the base case and sensitivity cases 4 PUBLIC

  5. Cascading Analysis Cases and Contingencies Study cases: Secure summer peak cases (Year 2, Year 5 and Year 6) Secure off-peak cases (Year 3) For cascading analysis, ERCOT studies the following NERC contingencies for cascading analysis P2.2 (HV- Bus section fault), P2.3 (HV- Internal failure of non-bus tie breaker), P2.4 (Internal failure of bus tie breaker), P4 (HV - Fault plus stuck breaker), P4.6 (EHV Fault plus a stuck bus-tie breaker), P5 (HV - Fault plus relay failure to operate), P6 (N-1-1 with system adjustment); EE1 (N-1-1 without system adjustment), EE2 (Local area events affecting the Transmission System), EE3 (Wide area events affecting the Transmission System based on System topology such as loss of two generating stations) 5 PUBLIC

  6. Cascading Analysis Methodology Methodology Equipment trip settings: Relay loadability limits for transmission facilities identified by TSPs. If not available, the lower of 115% of emergency rating or 150% of normal rating Generator over and under voltage relays identified by Generator Owners Buses with UVLS protection schemes where voltages go below the under voltage triggering level Monitored Elements: All Transmission Elements connected at the BES level were monitored according to the ERCOT System Operating Limit Methodology for Planning and Operations Horizon 6 PUBLIC

  7. Cascading Analysis Procedure General Study Procedure Following a initiating contingency event, the study will trip elements if the post contingent voltages and branch flows exceed the relay trigger limits and re-solve power flow. The study will continue to trip elements until the cascade analysis terminating condition is reached. The study will determine the accumulated load loss as a result of a system cascade 7 PUBLIC

  8. Cascading Analysis Criteria(Screening Study) Screening criteria: An initiating contingency event is identified to be a potential cascade event if The accumulated load loss is greater than 6% of the total initial system load, The power flow does not converge - which may be a result of a potential voltage collapse condition, subject to additional confirmation, OR The number of cascade levels exceeds user-defined tiers A contingency causing potential cascade event will be studied in detail to determine if the event leads to an actual cascade condition 8 PUBLIC

  9. Flow Chart for Screening Study 9 PUBLIC

  10. Cascading Analysis Criteria (Detailed Study and Mitigation Plan) Criteria for potential system cascading: Power flow fails to converge following the event The accumulated amount of total load loss is greater than 6% of the total initial system load Criteria to development of mitigation plan: Amount of load shedding to prevent cascading i. For an N-1-1 (P6) type events: More than 100 MW load shedding if the total load shed required after the first contingency, but prior to the second contingency ii. For other events such as N-2 (EE1): More than 300 MW load shedding The likelihood of the event is also considered to determine necessity of mitigation project 10 PUBLIC

  11. Flow Chart for Detailed Analysis 11 PUBLIC

  12. Cascading Analysis Tool Tools Used for Cascading Analysis: Potential Cascading Modes (PCM) Purpose: screening study and load shedding analysis Company: V&R Energy System Research PowerWorld Simulator Purpose: Detailed analysis of the select contingencies Company: PowerWorld Corporation 12 PUBLIC

  13. References NERC TPL-001-4 Standard 2017 Regional Transmission Plan Report System Operating Limit Methodology for Planning and Operations Horizon 13 PUBLIC

  14. Question Yong Cheng Yong.cheng@ercot.com 1 4 PUBLIC

Related


More Related Content