Market Efficiency Recommendation 2019
"Learn about the recommendation to remove the RUC opt-out option from the 2019 State of the Market Report by the ERCOT Independent Market Monitor. This change aims to increase reliability for loads and improve market efficiency by eliminating unintended incentives and enhancing grid management. View figures and detailed insights supporting this crucial market update."
Download Presentation

Please find below an Image/Link to download the presentation.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author. If you encounter any issues during the download, it is possible that the publisher has removed the file from their server.
You are allowed to download the files provided on this website for personal or commercial use, subject to the condition that they are used lawfully. All files are the property of their respective owners.
The content on the website is provided AS IS for your information and personal use only. It may not be sold, licensed, or shared on other websites without obtaining consent from the author.
E N D
Presentation Transcript
Remove RUC opt-out: A recommendation from the 2019 State of the Market Report by the Independent Market Monitor (IMM) Carrie Bivens ERCOT IMM Director cbivens@potomaceconomics.com Wholesale Market Working Group ERCOT Public August 17, 2020
2019 State of the Market Recommendation No. 1 Remove the opt out option for resources receiving RUC instructions. History: The ability to opt out of RUC settlement was NPRR416, filed in 2011 and implemented in 2014 RUC instructions were far less frequent in 2019 than in 2011 due to a number of improvements made over the years. Issue: Provides an unintended incentive for resource owners to show as off and available in the COP for future hours some resources that they reasonably expect to commit. There are reduced incentives to submit accurate COPs. A resource owner may expect to commit a resource to solve a local congestion problem, but is not sure that that decision will be profitable, perhaps due to the unknown commitment decisions of other resources. If ERCOT issues a RUC instruction for the resource, the resource owner s assumptions regarding the status of other unit or units are confirmed, and the resource owner can use the opt-out provision to proceed with the commitment as originally planned with no negative consequences. Consequences: Less generation was committed in the COP after RUC opt out option added. Reduces ERCOT s situational awareness and ability to effectively manage the grid. ERCOT s market design relies on individual resource owners making commitment decisions based on available information. This COP behavior distorts that information. 2
SOM Figure 38: Capacity Commitment Timing July and August HE 12 through 20 3
SOM Appendix Figure A40: Large Supplier Capacity Commitment Timing July and August HE 17 4
SOM Appendix Figure A41: NOIE Capacity Commitment Timing July and August HE 17 5
Recommendation Remove the RUC opt-out option to increase reliability for loads and improve market efficiency 6